Engineering Design and Support for Tea Tree Gully Sustainable Sewers by GHD
SA Water Corporation · Awarded contract
AwardedEngineering Design and Support for Tea Tree Gully Sustainable Sewers by GHD
Awarded 17 Jan 2025
Awarded17 Jan 2025
Value$1,900,268.37
SupplierGHD Pty LtdABN 39 008 488 373
AgencySA Water Corporation
StateSA
CategoryWater & Sanitation
Expires in 1y 1mo2y 12mo term, 62% elapsed
Awarded 17 Jan 2025Expires 31 Dec 2027
About
SA Water Corporation awarded a contract to GHD Pty Ltd for engineering design services and construction phase support for the Tea Tree Gully Sustainable Sewers Stage 3 project.
Similar open tenders12
TenderCloses
Construction of Factory Road Sewage Rising Main – Gippsland WaterWater & Sanitation
23 Nov 2026
Enviro Care Chipping Services – City of Tea Tree Gully 3.5‑Year Contract with 2‑Year OptionEnergy & Environment
23 Nov 2026
Design and Construction of Disinfection Upgrades – Shepparton Water Treatment Plant (Goulburn Valley Water)Water & Sanitation
24 Nov 2026
Water Sensitive Urban Design Rectification — Gateway, Broadmeadows & Sassafras Sunbury (Hume City Council)Water & Sanitation
03 Dec 2026
Ballarat East Branch Sewer Project Stage 2 – Provision for CHWWater & Sanitation
14 Dec 2026
Design Support for Eyre Peninsula Desalination Project – SA Water (Acciona ECI)Water & Sanitation
31 Dec 2026
Ballarat East Branch Sewer Project Stage 2 – Provision for CHWWater & Sanitation
14 Dec 2026
Project Delivery by Paradise Alliance — Sunwater with GHD and CPB Contractors/Georgiou GroupWater & Sanitation
30 Jun 2027
Programmed Rain Garden and WSUD Cleaning – City of MitchamWater & Sanitation
04 Dec 2026
Texas Wastewater Treatment Plant Upgrade - Civil and Mechanical WorksWater & Sanitation
20 Nov 2026
Sludge Dewatering Services for Cootamundra Sewage Treatment Plant — Cootamundra-Gundagai Regional CouncilWater & Sanitation
19 Nov 2026
Plumbing Services and Works for East Gippsland Shire Council Infrastructure (Panel)Water & Sanitation
09 Dec 2026
Other similar contracts12
Contract and supplierAwarded value
Completion of Tea Tree Gully Sustainable Sewers Program Stage 3Water & SanitationFULTON HOGAN UTILITIES P/L
$5,949,973.4
Engineering Support for Sewerage Upgrades in Nhulunbuy and GaliwinkuWater & SanitationGHD SERVICES PTY LTD
$95,115
Functional Design Development for MT030 Long Gully PS23 Sewer Compliance ProjectWater & SanitationGHD Pty Ltd
$699,193
Hydraulic Engineering Services for Water and Sewerage Network Planning in DarwinWater & SanitationGHD Pty Ltd
$119,047.5
Water, Sewer and Drainage Design Consultancy Awarded to GHDConsultancy & LegalGHD PTY LTD
$17,696.58
Deep Creek Corridor Sewer and Stormwater Rehabilitation Design Services by GHD Pty LtdWater & SanitationGHD Pty Ltd
$659,985.9
Interim Stakeholder Support for Tea Tree Gully Sustainable Sewers awarded to TSA RILEY (SA)Water & SanitationTSA RILEY (SA)
$634,719.36
Design Engineering Services for Building Construction and Maintenance by GHD Pty LtdConstructionGHD Pty Ltd
$310,336
Design Services for Angle Vale Stage 3 by GHD PTY LTDConsultancy & LegalGHD PTY LTD
$520,030.5
Sewerage and Drainage Upgrade Design Consultancy for Darwin-WeemolInfrastructureGHD Pty Ltd
$29,384
Engineering Design Services Provided by GHD PTY LTD to the Department of Infrastructure, Transport, Regional Development, Communications, Sport and the ArtsInfrastructureGHD PTY LTD
$19,237
Functional Design Development for Eaglehawk Sewer Compliance by GHD Pty LtdWater & SanitationGHD Pty Ltd
$475,423
Suppliers similar to GHD Pty Ltd8
SupplierContracts
GovMarket
We do the hard work.
You win the work.
We find the tenders, read the documents and track who wins, so your time goes on bids you can win.
–open water and sanitation tenders right now
–new in the last 7 days
–contracts awarded in the last 12 months
7 days free, then $59/AUD per month
Revenue from government work$312K won so far