Refurbishment of Aged Care Wards AC1 and AC2 at Royal Park Campus
Royal Melbourne Hospital Capital Works · Awarded contract
AwardedRefurbishment of Aged Care Wards AC1 and AC2 at Royal Park Campus
Awarded 19 Feb 2024
Ended 2y 1mo ago8mo term
Awarded 19 Feb 2024Expired 6 Oct 2024
About
Royal Melbourne Hospital Capital Works awarded a contract to Greenphase Pty Ltd for the refurbishment of aged care wards AC1 and AC2 at the Royal Park Campus, located at 34-54 Poplar Road, Parkville, Victoria, Building 17.
The project aimed to restore the use of these wards following their closure due to COVID-19 transmission issues.
The contract value is AUD 204,460.
Similar open tenders12
TenderCloses
Anti‑Ligature Refurbishment and Upgrades — Mental Health Wards, Princess Alexandra Hospital (Woolloongabba QLD)Construction
16 Nov 2026
Refurbishment of Main Ward Block Levels 2, 4, 6 and 7 – Alfred Hospital Urgent Infrastructure Main WorksConstruction
13 May 2027
Northern Hospital Redevelopment Stage 2 – Main Works for New Emergency Department and Inpatient UnitConstruction
01 Dec 2027
New Women's and Children's Hospital Construction – 1 Gaol Road, Adelaide (Circa 140,000 m²)Construction
31 Dec 2031
Northern Hospital Redevelopment Stage 2 – New Emergency Department and Inpatient Unit WorksConstruction
01 Dec 2027
Ballarat Base Hospital Redevelopment and Expansion — Stage 3 Final Stage Delivered by BuiltConstruction
30 Nov 2026
Ausgrid HV Augmentation and Early Works for Apex Park Redevelopment — Cessnock City CouncilConstruction
11 Nov 2026
Construction of Clinical Building for Warrnambool Base Hospital Redevelopment – Main WorksConstruction
20 Nov 2027
Managing Contractor for CSIRO APLR Stage 2 – Upgrade and Refurbishment of ACDP PC3/PC4 Laboratories and Large Animal FacilitiesConstruction
17 Dec 2026
Design and Construct Dalby Karingal RACF Upgrades – Darling Downs Hospital and Health ServiceConstruction
27 Nov 2026
Refurbishment and Design of Amenities Block – The Hall State School, Wandal QLDConstruction
13 Nov 2026
Construction of Clinical Building for Warrnambool Base Hospital Redevelopment (Main Works)Construction
20 Nov 2027
Other similar contracts12
Contract and supplierAwarded value
Refurbishment of AC1 and AC2 Buildings at Royal Park CampusConstructionMAW Building & Maintenance Pty Ltd
$1,816,187
Refurbishment of Royal Park Aged Care 3 into Telehealth FacilityConstructionJ Three Construction
$23,655
Refurbishment of BreastScreen Clinic at Royal Park Campus Buildings 6 & 7ConstructionGray Puksand
$88,200
Stage 2 Refurbishment Works at Craigieburn Community HospitalConstructionarete Australia
$3,216,506.7
Refurbishment of Wards 14A and 14B at The Canberra HospitalConstructionShape Australia Pty Limited
$17,712,184.6
Refurbishment of Ward G54 at SCGH by Bayside Australia 2000 Pty LtdConstructionBayside Australia 2000 Pty Ltd
$69,028
Remodelling of Aged Care at Harvey HospitalConstructionN/A
$16,362
Refurbishment of Renal, Security, Accommodation and Equipment Store at Prince of Wales HospitalConstructionRenascent Australia Pty Ltd
$14,410,976.8
C14 Ward Refurbishment at Sir Charles Gairdner HospitalConstructionBuilt (Built Pty Ltd)
$1,409,917
Architectural Design Services for Ward C16 Refurbishment at Sir Charles Gairdner HospitalConstructionSK Architecture Pty Ltd
$67,547
Refurbishment of Watling Walk Retail Precinct at Sir Charles Gairdner HospitalConstructionBuilt (Built Pty Ltd)
$1,390,508
Refurbishment of Ward C16 at Sir Charles Gairdner Hospital by Built Pty LtdConstructionBuilt (Built Pty Ltd)
$598,301
GovMarket
We do the hard work.
You win the work.
We find the tenders, read the documents and track who wins, so your time goes on bids you can win.
–open construction tenders right now
–new in the last 7 days
–contracts awarded in the last 12 months
7 days free, then $59/AUD per month
Revenue from government work$312K won so far