Replacement of Main Switchboard at QCC AGM Carpark
Arts Queensland · Awarded contract
AwardedReplacement of Main Switchboard at QCC AGM Carpark
Awarded 21 Dec 2021
Awarded21 Dec 2021
Value$67,496.00
SupplierSTEELE WROBEL QUANTITY SURVEYORS
AgencyArts Queensland
StateQLD
CategoryConstruction
About
Arts Queensland awarded a contract to Steele Wrobel Quantity Surveyors for the replacement of the main switchboard at the QCC AGM Carpark.
The contract value is AUD 67,496 and was procured through a select method under the building construction and maintenance category.
Source recordLEVEL 3, BOWMAN HOUSE, 276 EDWARD STREET, BRISBANE QLD 4000
Similar open tenders12
TenderCloses
Echuca Headquarters Main Switchboard Renewal – Campaspe Shire CouncilConstruction
10 Dec 2026
Supply and Installation of Chiller Plant, Cooling Tower and Main Switchboard Upgrade – Caloundra Indoor StadiumConstruction
17 Nov 2026
Principal Contractor (Medium Works with Design) for Accessibility Improvements at Gordonvale State SchoolConstruction
25 Nov 2026
Fraser Coast Regional Council — Sewerage Pump Stations Switchboard Replacement (Design & Construct)Water & Sanitation
12 Nov 2026
Colonel Light Centre Electrical Infrastructure Renewal – Main Switchboard, Distribution Boards & Generator InstallationInfrastructure
20 Nov 2026
Fire Alarm System Replacement and Carpark Fire Panel Reconfiguration — Gladstone Entertainment and Convention CentrePublic Safety & Security
24 Nov 2026
Workcover WA – Replacement of Existing SwitchboardsInfrastructure
23 Nov 2026
Replacement of Four Kitchenettes – Edmund Sheppard Courthouse, 31 Walker Street, TownsvilleConstruction
13 Nov 2026
Prequalified Panel for Substation Civil Works and Maintenance – Energy Queensland (Queensland)Energy & Environment
09 Nov 2026
Toolooa State High School – Stage 2 Accessibility and Connectivity ConstructionConstruction
10 Nov 2026
City of Moreton Bay – Building Construction Services Panel Arrangement (Small to Large Projects)Construction
13 Nov 2026
ACM Removal and External Repaint – Happy Valley State School, Mount IsaConstruction
17 Nov 2026
Other similar contracts12
Contract and supplierAwarded value
Replacement of Main Switchboard at QCC AGM Carpark by Steele Wrobel Quantity SurveyorsConstructionSTEELE WROBEL QUANTITY SURVEYORS
$101,092
Replacement of Main Switchboard at QCC AGM Carpark by Kane ConstructionsConstructionKANE CONSTRUCTIONS (QLD) PTY LTD
$1,716,883.41
Replacement of Main Switchboard at QCC AGM CarparkConstructionAUTOMATION IT (QLD) PTY LTD
$50,792.5
Replacement of Main Switchboard at AGM Carpark for Arts QueenslandConstructionJACOBS GROUP (AUSTRALIA) PTY LIMITED
$74,262.1
Replacement of AGM Carpark Main Switchboard for Arts QueenslandConstructionJACOBS GROUP (AUSTRALIA) PTY LIMITED
$28,602.2
Replacement of AGM Carpark Main Switchboard for Arts QueenslandConstructionJACOBS GROUP (AUSTRALIA) PTY LIMITED
$93,740.9
Replacement of AGM Carpark Main Switchboard for Arts QueenslandConstructionJACOBS GROUP (AUSTRALIA) PTY LIMITED
$40,507.5
Replacement of Main Switchboard at QCC AGM Carpark by HoneywellConstructionHONEYWELL LIMITED
$68,111.36
Replacement of QPAC Main Switchboard by Steele Wrobel Quantity SurveyorsConstructionSTEELE WROBEL QUANTITY SURVEYORS
$370,752
Replacement of QPAC Main Switchboard by Steele Wrobel Quantity SurveyorsConstructionSTEELE WROBEL QUANTITY SURVEYORS
$257,730
Award of QCC Site Wide Carpark Painting Contract to Steele Wrobel Quantity SurveyorsConstructionSTEELE WROBEL QUANTITY SURVEYORS
$115,368
Replacement of QPAC Main Switchboard by Wilson ArchitectsConstructionWilson Architects Pty Ltd
$731,116
GovMarket
We do the hard work.
You win the work.
We find the tenders, read the documents and track who wins, so your time goes on bids you can win.
–open construction tenders right now
–new in the last 7 days
–contracts awarded in the last 12 months
7 days free, then $59/AUD per month
Revenue from government work$312K won so far